Concluded Xingu OperationPublicado em: 15/01/2018
Completed the door to door delivery of 14 transformers to Xingu Substation, in the Amazon region, which will be responsible for transforming part of the high voltage energy of the Belo Monte Hydroelectric Plant, the fourth largest of installed capacity in the world.Transdata carried out overland haulage of 06 transformers 10.40 x 04.00 x 05.10 meters - 219 tonnes from…