Operation:
Transport by hydraulic gantry systems.
Highlight:
Supporting the installation of the ship loaders CN03 and CN04, at the terminal port Porto da Madeira in São Luís, State of Maranhão, Transdata performed the internal haulage of the main girder by two 1,000-tonne hydraulic gantry systems to transfer the equipment along nine meters.
The expansion of the port terminal Porto da Madeira is the largest Latin America port project and part of the BRL $ 7 billion investment in port logistic of the Brazilian Mining largest company. Its goal is transporting the production of the most important facility expansion project of the company called Serra Sul in Carajás, State of Pará.
SPECIFICATIONS
Cargo Dimensions: |
02 x 94.00 x 08.00 x 07.50 meters - 800 tonnes |
Main Equipment: |
02 1,000-tonne Hydraulic Gantry Systems |